THe Kings Road Regeneration Scheme means road closures are inevitable while works are carried out. Here are the Official Notices:
EAST SUSSEX COUNTY COUNCIL
NOTIFICATION OF TEMPORARY CLOSURE OR RESTRICTIONS
| Road(s) Affected and Classification London Road A2102, Kings Road (UC3145a) and DPROW 98 (Steps running between Kings Road and London Road). | |
|
Type of Restriction Temporary Road Closures, Temporary Suspension of existing One Way restriction and Temporary Footpath Closure
|
|
| Required By Mark Coates | |
| Address: Highways House, 41-45 Broadwater Road, Welwyn Garden City, Herts, AL7 3AX | |
| Reason for Order: To facilitate Kings Road regeneration works | |
| Starting Order: 2nd March 2009 | |
| Approximate Duration: 14 weeks | |
| (NOTE: The restriction will be lifted as soon as the work is completed. The order will include an allowance of extra time to cover unforeseen difficulties extending the estimated duration of work.)
|
|
| In Case of Query, contact: Mark Coates 01707 356279 | |
| Undertaking/Contractor: Mouche1 | |
| Traffic Co-ordination: Peter Philips (01424) 783337 | |
| Outside Office Hours: 01707 356279
|
|
| PROPOSED RESTRICTIONS (Access to properties will be maintained at all times and unless otherwise stated pedestrian access will not be affected).
On 2nd March 2009, or soon after, Mouch1 will commence regeneration works at Kings Road and London Road St Leonards on Sea. Works will be carried out in the highway therefore it will be necessary to introduce the following temporary restrictions- Temporary Road closures at London Road (2 weekends only to minimise disruption to traffic) Temporary Road closure at Kings Road (14 weeks) Temporary Suspension of existing One Way restriction in Kings Road (14 weeks) to facilitate deliveries during works Temporary Footpath closure at DPROW 98 (steps running between Kings Road and London Road) (4 weeks) |
|
| ORDER REQUIRED
Temporary Road closures at London Road from its junction with Shepherd Street to its junction with Pevensey Road Temporary Road closure at Kings Road for its entire length and temporary suspension of existing one way for its entire length Temporary Footpath closure at DPROW 98 (Kings Road steps) for its entire length
|
|
| DIVERSION ROUTE AND CLASSIFICATION
London Road Closure Northbound diversion- Grand Parade (A259), Verulam Place (A259), Eversfield Place (A259), Schwerte Way (UC3160d), White Rock Road (UC3160c), Cambridge Road (A21), Bohemia Road (A21) and London Road (A2102) London Road Closure Southbound diversion- London Road (A21), Bohemia Road (A21), Cambridge Road (A21), White Rock Road (UC3160c), Schwerte Way (UC3160d), Eversfield Place (A259), Verulam Place(A259) and Grand Parade (A259) Kings Road Closure Northbound diversion- London Road (A2102), Norman Road (A2102b), Warrior Square (UC3160a), St Margarets Road (UC3160b) and St Johns Road (UC3145b) Kings Road Closure Southbound diversion- Hatherley Road (UC3146b), Southwater Road (UC3148a), Ellenslea Road (UC3147a), Chapel Park Road (UC3156a) and St Johns Road (UC3145b) DPROW 98 Footpath Closure- London Road (A2102) footpath, Kings Road (UC3145a) footpath and vice versa |
|
* The starting date cannot be guaranteed. Anyone particularly concerned should contact the office below for up to date information.
Hastings Highway Manager
Century House
100 Menzies Road
St Leonards-on-Sea TN38 9BB
Date
C/T/T4/
EAST SUSSEX COUNTY COUNCIL
NOTIFICATION OF TEMPORARY CLOSURE OR RESTRICTIONS
| Road(s) Affected and Classification | Cross Street (U3144a) |
|
Type of Restriction |
Temporary Road Closure |
| Required By | Morrisons Utility Services |
| Address: | Firsland Park Industrial estate, Henfield Road, Albourne, West Sussex, BN6 9JJ |
| Reason for Order: | To facilitate essential gas main replacement work |
| Starting Order: | 11/03/2009 |
| Approximate Duration: | 3 Weeks |
| (NOTE: The restriction will be lifted as soon as the work is completed. The order will include an allowance of extra time to cover unforeseen difficulties extending the estimated duration of work.)
|
|
| In Case of Query, contact: | Tim Sheehan 07771 957618 |
| Undertaking/Contractor: | Morrisons Utility Services 07880 781783 |
| Traffic Co-ordination: | Peter Philips (01424) 783348 |
| Outside Office Hours
|
07771 957618 |
| PROPOSED RESTRICTIONS (Access to properties will be maintained at all times and unless otherwise stated pedestrian access will not be affected).
On 11th March 2009, or soon after Morrisons will commence essential gas mains replacement works at Cross Street, St Leonards on Sea. Works will be carried out in the highway it will therefore be necessary to temporarily close the western end of Cross Street for the duration of the works. It will also be necessary to temporarily reverse the existing one way at Cross Street to facilitate traffic exiting South Street and Crystal Square car park. |
|
| ORDER REQUIRED
Temporary Road Closure at Cross Street from its junction with London Road to its junction with South Street. Temporary reversal of one way at Cross Street.
|
|
| DIVERSION ROUTE AND CLASSIFICATION
Westbound Traffic Via; Western Road (U3144c), Norman Road (A2102b), Warrior Square (U3160a), Warrior Square (U3144g), Grand Parade (A259), London Road (A2102) Access from South Street Via; Cross Street (U3144a), Western Road (U3144c), Norman Road (A2102b), Warrior Square (U3160a), Warrior Square (U3144g), Grand Parade (A259), London Road (A2102)
|
|
* The starting date cannot be guaranteed. Anyone particularly concerned should contact the office below for up to date information.
Hastings Highway Manager
Century House
100 Menzies Road
St Leonards-on-Sea TN38 9BB
12th February 2009
C/T/T4/CP